Wisconsin Administrative Code (Last Updated: January 10, 2017) |
Agency Trans. Department of Transportation |
Chapter 400. Wisconsin Environmental Policy Act Procedures For Department Actions |
Section 400.07. Action designation and environmental documentation.
Latest version.
- (1) The designations, EIS and CE shall be used to categorize department actions. Actions designated EIS actions shall be considered major actions, and actions designated CE shall be considered categorical exclusions. An EA and an ER describe procedures to be followed to categorize department actions. The EA process yields a determination whether an action requires an EIS or a finding of no significant impact. The ER process confirms whether an action falls within a categorical exclusion or requires further evaluation and documentation.(2) Except for actions designated CE actions which do not require any environmental documentation, actions and procedures designated EIS, EA or ER shall require the following environmental documentation:(a) EIS or LEIS. An EIS action is a major action. An LEIS may be prepared for a major and significant new proposal.1. An environmental impact statement, or EIS, shall be prepared for major actions.2. A legislative environmental impact, or LEIS, may be prepared when a major and significant new proposal consists of a report or recommendation of the department on a proposal for legislation initiated by the department that is not within the scope of any categorical exclusion.(b) EA, SEE or screening sheet. An EA is a procedure followed for an action for which the significance of the environmental impact is not clearly established. An EA, SEE or screening sheet may be used as follows:1. An EA shall be prepared for those project actions for which the significance of the environmental impact is not clearly established. If it is concluded from the analysis in the EA that the action is a major action, an EIS shall be prepared. If it is concluded from the analysis in the EA that the action is not a major action, the EA shall be revised to constitute a FONSI, and the FONSI shall serve as the environmental document. The FONSI shall be prepared only after availability of the EA for public and cooperating agency review and comment and the incorporation of any appropriate revisions resulting from the public involvement process. Where a permit will be required or other agency coordination is specifically required by law, the FONSI may serve as the vehicle for such permit or coordinating agency approval.2. A SEE may be prepared in the case of proposals contained in system plans, if it is concluded they are major and significant new proposals. If it is concluded from an analysis of the system plan that it does not contain any major and significant new proposals, a clear statement of that determination may be incorporated within the system plan or as a separately identifiable and retained record of the department's determination.3. In the case of reports or recommendations of the department on proposals for legislation initiated by the department, if it is concluded from the screening sheet they contain major and significant new proposals, an LEIS may be prepared. If it is concluded from the screening sheet that they do not contain any major and significant new proposals or are within the scope of any categorical exclusion, a clear statement of that determination may be included on the screening sheet.(c) ER. An ER is a procedure followed for an action that is likely to fit the criteria for a conditional categorical exclusion in 23 CFR 771.117 (d), April 1, 1998 or federal aviation administration order 5050.4A, chapter 3, paragraph 23.a., October 8, 1985, or otherwise requires coordination with or concurrence of another agency. An environmental report, or ER, shall be prepared to demonstrate whether the proposed action does fit the criteria or conditions for approval as a categorical exclusion and has been properly coordinated with other agencies having jurisdiction by law over specific activities. The ER shall serve as the department's record of coordination with other agencies having jurisdiction over specific activities, including the following activities:1. Construction-related activities including, but not limited to, stream crossings, fills in wetlands and temporary structures in or over streams or wetlands.2. Defined land use acquisition including, but not limited to, the acquisition of agricultural lands, historic or archeological sites, and state, county or national forest lands.
History:
Cr.
Register, April, 1992, No. 436
, eff. 5-1-92; am. (1), (2) (intro.), (a), (b) and (c) (intro.),
Register, February, 1999, No. 518
, eff. 3-1-99.