Section 28.09. Application process.  


Latest version.
  • (1)  Applications for harbor assistance program grants shall be submitted to the department in a manner and form prescribed by the department. Forms shall be available without charge.
    (2)  Each application shall include the following information:
    (a) A resolution officially adopted by the eligible applicant containing:
    1. A formal request for assistance.
    2. The name of the eligible applicant's representative authorized to sign forms or claims. The representative shall be the applicant's contact person for the project. If there are more than one, all their names shall be included in the application.
    3. A statement that the eligible applicant will accept responsibility for operation and maintenance of the proposed project after completion of the work funded.
    4. A statement that the proposed project is consistent with the harbor development plan or with the comprehensive plan of the local government if a plan or plans have been adopted. A copy of any plan shall be attached to the application.
    5. A statement that the proposed project is consistent with the 3-year harbor development statement of intentions submitted by the eligible applicant as required by s. Trans 28.10 .
    6. A statement that the eligible applicant agrees to provide the department, in a timely manner, additional analysis or documentation supporting the application, whenever the department considers it necessary during the application review process.
    7. A statement that the eligible applicant agrees to provide required matching funds up to a stated maximum at the time and in the manner specified in the grant agreement.
    (b) A narrative description of the project which, at a minimum, shall include:
    1. A detailed description of the work to be performed including plans, drawings, sounding reports or other information necessary to fully describe the project.
    2. A detailed description of the means by which the work is to be performed.
    3. A statement of justification and reasons for accomplishing the project, including a discussion of possible alternatives in type and scope to the project.
    4. A map, sketch, or other depiction of the project site.
    5. A statement of current ownership of the project site and facilities and of the ownership proposed upon completion of the project.
    6. A time schedule for performing major project tasks.
    (c) A detailed estimate of project cost, indicating the eligible applicant's cost share, amount of state funding requested, other sources or potential sources of funds and full description of timetables and conditions affecting funds other than funds already budgeted by the applicant.
    (d) An estimate of project development costs, not included as estimated project costs, that are essential to the success of the project. This may include, for example, the value of existing land and facilities, the cost of additional site development and the cost of storage or transfer facilities.
    (e) An estimate of the eligible applicant's annual revenues from the project if completed, or of revenues lost if the project is not completed, and an estimate of the annual costs necessary to maintain the project property.
    (f) An estimate of the number and type of jobs directly attributable to the proposed project, or of those jobs lost if the project is not completed. The estimates shall be supported by a description of the means by which the number of jobs is calculated.
    (g) A list of commodities and a disclosure of the tonnage of waterborne commerce using the project property and expected to use the project property if the project is completed, with origin and destination information.
    (h) A list of permits necessary for the project to proceed and, if the permits have not been obtained, a description of the actions taken or to be taken to obtain the permits.
    (i) A description of the probable environmental impact of the project. Copies of environmental reports, environmental screening worksheets, environmental assessments, and environmental impact statements shall be provided.
    (j) An estimated annual number of passengers that will be affected by the project.
    (3)  If an eligible applicant fails to supply required information or supplies erroneous information, the department may disapprove the application.
    (4)  The eligible applicant shall submit an application to the department by August 1 in order to receive primary consideration for funding during the following calendar year. If funds are available, applications may be submitted by March 15, 1985, and by February 1 of each year thereafter, for funding in the same calendar year. The department may waive the requirements in this subsection for emergency repair projects.
History: Cr. Register, February, 1985, No. 350 , eff. 3-1-85; correction in (2) (a) 5., made under s. 13.93 (2m) (b) 7., Stats., Register, December, 1987, No. 384 ; CR 01-117 : am. (2) (a) 5. and cr. (2) (j) Register March 2002 No. 555 , eff. 4-1-02; CR 05-019 : am. (2) (a) 3., 6., 7., (e), (3) and (4) Register July 2005 No. 595 , eff. 8-1-05.

Note

Application forms for harbor assistance program grants may be obtained without charge from: Manager, Harbor Assistance Program, P.O. Box 7914, Madison, Wisconsin 53707-7914. Microsoft Windows NT 6.1.7601 Service Pack 1