Wisconsin Administrative Code (Last Updated: January 10, 2017) |
![]() |
Agency SPS. Department of Safety and Professional Services |
![]() |
Chapters 301-. Safety, Buildings, and Environment |
![]() |
Chapters SPS361-366. Commercial Building Code |
![]() |
Chapter SPS361. Administration And Enforcement |
![]() |
SubChapter III. Plan Review and Related Functions |
Section 361.32. Permission to start construction.
Latest version.
- (1) A building owner may request and the department or its authorized representative may grant permission to start construction for the footings and foundations upon submission of construction documents under s. SPS 361.31 .(2) A building owner who has been granted permission to start construction of the footings and foundations may proceed at the owner's own risk without assurance that a conditional approval for the building will be granted.(3) The department shall review and make a determination on an application for permission to start construction of the footings and foundations within 3 business days of receipt of the application and all forms, fees, construction documents and information required to complete the review.
History:
CR 00-179
: cr.
Register December 2001 No. 552
, eff. 7-1-02; correction in (1) made under s.
13.92 (4) (b) 7.
, Stats.,
Register December 2011 No. 672
.