Wisconsin Administrative Code (Last Updated: January 10, 2017) |
Agency SPS. Department of Safety and Professional Services |
Chapters 301-. Safety, Buildings, and Environment |
Chapters SPS326-360. General, Part II |
Chapter SPS341. Boilers And Pressure Vessels |
SubChapter V. Nuclear Power Plants |
Section 341.53. Application.
Latest version.
- (1) General. This subchapter applies to all nuclear power facilities existing on or after June 1, 2012.(2) NRC requirements. Construction, installation, operation, alterations and repairs for nuclear facility components that are regulated by the NRC shall comply with all applicable NRC regulations.
Cr.
Register, February, 1988, No. 386
, eff. 3-1-88; correction made under s.
13.92 (4) (b) 7.
, Stats.,
Register December 2011 No. 672
;
CR 11-047
: renum. 341.53 to be (1) and am., cr. (1) (title), (2)
Register May 2012 No. 677
, eff. 6-1-12.
Note
See
10 CFR 50.55
a to 50.57 for applicable NRC regulations.