Wisconsin Administrative Code (Last Updated: January 10, 2017) |
Agency PSC. Public Service Commission |
Chapter 183. Joint Local Water Authorities |
Section 183.04. Commission review of information submitted.
Latest version.
- (1) Upon receipt of an application for a certificate identified in s. PSC 183.02 (2) , the commission shall review the application and:(a) determine if the proposal in the application requires a hearing. After the hearing, or after the determination that no hearing is required,(b) issue a certificate of public convenience and necessity pursuant to s. 66.0823 (8) (c) , Stats., or(c) deny the application for a certificate of public convenience and necessity pursuant to s. 66.0823 (8) (b) , Stats.(2) The commission shall grant or deny the application within 90 days of the date the application is received, unless extended by the commission for good cause.
History:
Cr.
Register, August, 1999, No. 524
, eff. 9-1-99;
corrections in (1) (b) and (c) made under s. 13.93 (2m) (b) 7., Stats.,
Register April 2007 No. 616
.