Section 134.29. Installation test.  


Latest version.
  • No meter shall be used to meter gas consumption for billing purposes unless it was tested and found correct, as defined in s. PSC 134.27 not longer than 15 months previous to its use. The first test on a meter or a retest after a major overhaul shall include a check of the registering device and linkages.
History: Cr. Register, February, 1959, No. 38 , eff. 3-1-59; am. Register, April, 1969, No. 160 , eff. 5-1-69.