Section 333.08. Construction.  


Latest version.
  • (1)  Construction of a new dam or reconstruction of an existing dam may not begin until the department approves the plans and specifications submitted under s. NR 333.05 .
    (2)  Alterations to any plans or specifications that were approved by the department under s. NR 333.05 which will affect the flood flow capacity or structural integrity of a dam shall be approved by the department before construction or reconstruction of the dam.
    (3)  All dams shall be constructed or reconstructed under the supervision of a professional engineer registered in the state of Wisconsin. The supervising engineer shall, within 10 days after completing the construction or reconstruction of a dam, submit a statement indicating that the dam was constructed or reconstructed in accordance with the plans and specifications approved by the department under s. NR 333.05 .
    (4)  As-built plans shall be submitted to the department within 30 business days after the completion of construction or reconstruction of a dam.
History: Cr. Register, May, 1985, No. 353 , eff. 6-1-85; CR 00-136 : am. (3), Register July 2001, No. 547 eff. 8-1-01.