Section 200.10. Time periods for action on permit applications and modification requests.  


Latest version.
  • (1)  Within 100 business days of receipt of a complete permit application or request for modification of an existing permit the department shall publish a class 1 notice under ch. 985 , Stats. , indicating its intended action.
    (2)  Where a complete reissuance application has been received at least 180 calendar days prior to the permit expiration date, the department shall, at least 25 business days prior to the expiration date, publish a class 1 notice under ch. 985 , Stats. , indicating its intended action. Where a complete reissuance application is not received at least 180 calendar days prior to the permit expiration date, the time deadline in sub. (1) shall apply.
    (3)  The department's final decision on a permit application or request for modification shall be made within 50 business days after completion of the hearing process under s. 283.49 , Stats., and consideration of the environmental impact of the project as required by s. 1.11 , Stats.
    (4)  The time deadlines in subs. (1) to (3) are not applicable to permit applications or modification requests submitted to the department by a municipality.
    (5)  The time deadlines in sub. (2) are not applicable if the department determines, pursuant to s. 283.53 , Stats., that the permittee is not in substantial compliance with all the terms, conditions, requirements and schedules of compliance of the expiring permit.
History: Cr. Register, May, 1985, No. 353 , eff. 6-1-85 ; correction in (3) made under s. 13.93 (2m) (b) 7., Stats., Register, November, 1996, No. 491 ; cr. (5), Register, November, 1999, No. 527 , eff. 12-1-99.

Note

One hundred business days is approximately 140 calendar days; 50 business days is approximately 70 calendar days; 25 business days is approximately 30 calendar days. Microsoft Windows NT 6.1.7601 Service Pack 1