Wisconsin Administrative Code (Last Updated: January 10, 2017) |
![]() |
Agency ATCP. Department of Agriculture, Trade and Consumer Protection |
![]() |
Chapters 20-54. Agricultural Resource Management |
![]() |
Chapter 33. Fertilizer And Pesticide Bulk Storage |
![]() |
SubChapter V. Sumps |
Section 33.36. Sumps; general.
Latest version.
- If a mixing and loading pad or secondary containment structure drains to a sump, the sump shall be all of the following:(1) Designed, constructed and maintained to contain liquid that drains to the sump.(2) Liquid-tight.(5) Inspected and approved at the time of construction, in the same manner as a mixing and loading pad inspected under s. ATCP 33.32 (6) , if the sump is constructed of portland cement concrete on or after November 1, 2006. The operator shall provide DATCP with a copy of the inspection report and approval.(6) Routinely inspected and maintained to ensure compliance with this section.(7) Repaired, when necessary, according to good engineering practice and manufacturer specifications.(8) Removed if it cannot be maintained in compliance with this section, or if corrective action is needed to remove contamination from beneath the sump. An operator shall remove a leaking sump unless the sump is repaired and remains liquid-tight for at least 2 years after the date of repair.