- (1) Land use and commercial enterprises. An owner shall make reasonable efforts to ascertain and accommodate any land use or commercial enterprise located on a nonparticipating property within 0.5 mile of a proposed wind turbine site if the land use or commercial enterprise exists when the owner gives notice under s. PSC 128.105 (1) , or if complete publicly-available plans for construction are on file with a political subdivision within 30 days of the date the owner gives notice under s. PSC 128.105 (1) .(2) Agricultural use. An owner shall design a wind energy system to reasonably minimize the conversion of land from agricultural use.
CR 10-057
: cr.
Register February 2011 No. 662
, eff. 3-1-11.