Section 810.37. Cryptosporidium treatment requirement compliance schedule.  


Latest version.
  • (1)  Following initial bin classification under s. NR 810.34 (3) , filtered systems shall provide the level of treatment for Cryptosporidium required under s. NR 810.35 according to the schedule in sub. (3) .
    (2)  Following initial determination of the mean Cryptosporidium level under s. NR 810.36 (1) (a) , unfiltered systems shall provide the level of treatment for Cryptosporidium required under s. NR 810.36 according to the schedule in sub. (3) .
    (3)  Cryptosporidium treatment compliance dates.
    Cryptosporidium Treatment Compliance Dates Table - See PDF for table PDF
    1 The department may allow up to an additional 2 years for complying with the treatment requirement for systems making capital improvements.
    (4)  If the bin classification for a filtered system changes following the second round of source water monitoring, as determined under s. NR 810.34 , the system shall provide the level of treatment for Cryptosporidium required under s. NR 810.35 on a schedule approved by the department.
    (5)  If the mean Cryptosporidium level for an unfiltered GWUDI system changes following the second round of monitoring, as determined under s. NR 810.36 , and if the system is required to provide a different level of Cryptosporidium treatment under s. NR 810.36 due to this change, the system shall meet this treatment requirement on a schedule approved by the department.
History: CR 09-073 : cr. Register November 2010 No. 659 , eff. 12-1-10.