Wisconsin Administrative Code (Last Updated: January 10, 2017) |
![]() |
Agency NR. Department of Natural Resources |
![]() |
Chapters 200-299. Environmental Protection – Wisconsin Pollutant Discharge Elimination System |
![]() |
Chapter 216. Storm Water Discharge Permits |
![]() |
SubChapter III. Construction Site Storm Water Discharge Permits |
Section 216.43. Notice of intent requirements.
Latest version.
- (1) Forms. The landowner shall submit a notice of intent to the department on forms available from the department. Data submitted in the notice of intent forms shall be used as a basis for conferring coverage under a WPDES storm water permit.(2) Application fee. A storm water construction site application fee defined by Table 5 shall be submitted to the department with the notice of intent. - See PDF for table(3) Signature requirements. The notice of intent form shall be signed by the landowner as follows:(a) In the case of a corporation, by a principal executive officer of at least the level of vice president or by the officer's authorized representative having overall responsibility for the operation of the site for which a permit is sought.(b) In the case of a limited liability company, by a member or manager.(c) In the case of a partnership, by a general partner.(d) In the case of a sole proprietorship, by the proprietor.(e) For a unit of government, by a principal executive officer, ranking elected official or other duly authorized representative.
Note
The notice of intent form is available from the department website at
http://dnr.wi.gov/topic/Stormwater/construction/forms.html
or by contacting the storm water program in the bureau of watershed management at (608) 267-7694.